Planned activities for the Week of January 23-27

·        Southeast end of Horsetooth Reservoir

o   Installation of bases and bottom sections of new transmission poles using a small crane.

·        Pineridge

o   Drilling for final pole foundation will take most of the week due to underlying rock formation. Traffic control will be provided to avoid conflicts with trail use.